The GMAT examination asks you a few interesting sums based on the work and time topic. You, as a candidate, will have to keep in mind that you need to find the rate of work happening and that’s basically it: Work Rate = Total Work / Time Taken. ...
The GMAT examination asks you a few interesting sums based on the work and time topic. You, as a candidate, will have to keep in mind that you need to find the rate of work happening and that’s basically it:
Work Rate = Total Work / Time Taken.
Below, we have provided a few practice problems for your preparations. Let’s go through them all without any further ado.
Question 1
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
A. 1/4
B. 1/10
C. 7/15
D. 8/15
Solution:
A's 1 day's work = 1/15;
B's 1 day's work = 1/20;
(A + B)'s 1 day's work =(1/15 + 1/20) = 7/60.
(A + B)'s 4 day's work = (7/60 x 4) = 7/15.
Therefore, Remaining work = (1 – 7/15) = 8/15.
Answer: Option D
2. A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
A. 9 1/5 days
B. 9 2/5 days
C. 9 3/5 days
D. 10 days
Solution:
(A + B + C)'s 1 day's work = 1/4,
A's 1 day's work = 1/16.
B's 1 day's work = 1/12.
Therefore C's 1 day's work = 1/4 - (1/16 + 1/12) = (1/4 – 7/48) = 5/48.
So, C alone can do the work in 48/5 = 9 3/5 days.
Answer: Option C
3. A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
A. 12 days
B. 15 days
C. 16 days
D. 18 days
Solution:
A's 2 day's work = (1/20 x 2) = 1/10.
(A + B + C)'s 1 day's work = 1/20 + 1/30 + 1/60 = 6/60 = 1/10.
Work done in 3 days = 1/10 + 1/10 = 1/5.
Now, 1/5 work is done in 3 days.
Therefore, the whole work will be done in (3 x 5) = 15 days.
Answer: Option B
4. A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
A. 20 days
B. 22 ½ days
C. 25 days
D. 30 days
Solution:
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If the difference of time is 2 days, B takes 3 days.
If the difference of time is 60 days, B takes (3/2 x 60) = 90 days.
So, A takes 30 days to do the work.
A's 1 day's work = 1/30
B's 1 day's work = 1/90
(A + B)'s 1 day's work = 1/30 + 1/90 = 4/90 = 2/45
A and B together can do the work in 45/2 = 22 ½ days.
Answer: Option B
5. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
A. Rs. 375
B. Rs. 400
C. Rs. 600
D. Rs. 800
Solution:
C's 1 day's work = 1/3 – (1/6 + 1/8) = 1/3 – 7/24 = 1/24.
A's wages : B's wages : C's wages = 1/6 : 1/8 : 1/24 = 4 : 3 : 1.
C's share (for 3 days) = Rs. (3 x 1/24 x 3200) = Rs. 400.
Answer: Option B
6. A and B can complete a work in 15 days and 10 days respectively. They started doing the work together, but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :
A. 8 days
B. 10 days
C. 12 days
D. 15 days
Solution:
(A + B)'s 1 day's work = (1/15 + 1/10) = 1/6.
Work done by A and B in 2 days = (1/6 x 2)= 1/3.
Remaining work = (1 – 1/3) = 2/3.
Now, 1/15 work is done by A in 1 day.
Therefore, 2/3 work will be done by A in (15 x 2/3) = 10 days.
Hence, total time taken = (10 + 2) = 12 days.
Answer: Option C
All the best for GMAT 2018!
Tell us your learning requirements in detail and get immediate responses from qualified tutors and institutes near you.
Post Learning Requirement