Quantitative GMAT Time and Work Problems and Solutions: Sample Numericals For Practice

The GMAT examination asks you a few interesting sums based on the work and time topic. You, as a candidate, will have to keep in mind that you need to find the rate of work happening and that’s basically it: Work Rate = Total Work / Time Taken. ...

Article Posted in: College Level Education

The GMAT examination asks you a few interesting sums based on the work and time topic. You, as a candidate, will have to keep in mind that you need to find the rate of work happening and that’s basically it:

Work Rate = Total Work / Time Taken.

Below, we have provided a few practice problems for your preparations. Let’s go through them all without any further ado.

Question 1

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

A. 1/4

B. 1/10

C. 7/15

D. 8/15

Solution:

A's 1 day's work = 1/15;

B's 1 day's work = 1/20;

(A + B)'s 1 day's work =(1/15 + 1/20) = 7/60.

(A + B)'s 4 day's work = (7/60 x 4) = 7/15.

Therefore, Remaining work = (1 – 7/15) = 8/15.

Answer: Option D

2. A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

A. 9 1/5 days

B. 9 2/5 days

C. 9 3/5 days

D. 10 days

Solution:

(A + B + C)'s 1 day's work = 1/4,

A's 1 day's work = 1/16.

B's 1 day's work = 1/12.

Therefore C's 1 day's work = 1/4 - (1/16 + 1/12) = (1/4 – 7/48) = 5/48.

So, C alone can do the work in 48/5 = 9 3/5 days.

Answer: Option C

3. A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

A. 12 days

B. 15 days

C. 16 days

D. 18 days

Solution:

A's 2 day's work = (1/20 x 2) = 1/10.

(A + B + C)'s 1 day's work = 1/20 + 1/30 + 1/60 = 6/60 = 1/10.

Work done in 3 days = 1/10 + 1/10 = 1/5.

Now, 1/5 work is done in 3 days.

Therefore, the whole work will be done in (3 x 5) = 15 days.

Answer: Option B

4. A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

A. 20 days

B. 22 ½ days

C. 25 days

D. 30 days

Solution:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If the difference of time is 2 days, B takes 3 days.

If the difference of time is 60 days, B takes (3/2 x 60) = 90 days.

So, A takes 30 days to do the work.

A's 1 day's work = 1/30

B's 1 day's work = 1/90

(A + B)'s 1 day's work = 1/30 + 1/90 = 4/90 = 2/45

A and B together can do the work in 45/2 = 22 ½ days.

Answer: Option B

5. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

A. Rs. 375

B. Rs. 400

C. Rs. 600

D. Rs. 800

Solution:

C's 1 day's work = 1/3 – (1/6 + 1/8) = 1/3 – 7/24 = 1/24.

A's wages : B's wages : C's wages = 1/6 : 1/8 : 1/24 = 4 : 3 : 1.

C's share (for 3 days) = Rs. (3 x 1/24 x 3200) = Rs. 400.

Answer: Option B

6. A and B can complete a work in 15 days and 10 days respectively. They started doing the work together, but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :

A. 8 days

B. 10 days

C. 12 days

D. 15 days

Solution:

(A + B)'s 1 day's work = (1/15 + 1/10) = 1/6.

Work done by A and B in 2 days = (1/6 x 2)= 1/3.

Remaining work = (1 – 1/3) = 2/3.

Now, 1/15 work is done by A in 1 day.

Therefore, 2/3 work will be done by A in (15 x 2/3) = 10 days.

Hence, total time taken = (10 + 2) = 12 days.

Answer: Option C

 

All the best for GMAT 2018!

Article Posted in: College Level Education
Tags: Education Examination Learning GMAT

MyPrivateTutor UAE

MyPrivateTutor is an online marketplace for all kinds of tutoring and learning services. We provide a platform to help learners find home tutors, online tutors, expert trainers,tutorial centers, training institutes and online tutoring schools. Learners can also find local classes, workshops, online courses and tutorials on a huge variety of topics. We operate in 12 countries worldwide and our community of learners, teachers and training businesses numbers over 200,000. We provide an opportunity for individual tutors and tutoring businesses to promote and grow their business.

Looking for Tutor or Coaching Class?

Tell us your learning requirements in detail and get immediate responses from qualified tutors and institutes near you.

Post Learning Requirement